Project - Week 15
Wednesday 6th DecemberPainting has started with a vengance. Alex completed the first coat of emulsion on all the rooms - less than 2 days work for him!! We hope to have most of the painting finished by Friday. | Thursday 7th DecemberSecond emulsion coat completed downstairs - just the bedrooms and bathrooms to go. Also, added yet more insulation to the roof space over the lounge and the coombes. | | Friday 8th DecemberPainting finished by Alex; the plumber returns to pipe in showers and finish upstairs toilets, and we wire the consumer unit in preparation for testing on circuits next week. | | |